May 14, 2019Asheville City Council
From the minutes, not yet reviewedCouncil changes a contract to implement the Blue Horizons Project for an additional two years, to expand the scope of the work.
Council voted to change its contract with Green Built Alliance to implement the Blue Horizons Project for an additional two years, to expand the scope of the work.
- Passed with the routine items, in one vote, without discussion.
- What the City says it's for: “The contract amendment will provide continued engagement and education opportunities on energy efficiency and renewable energy programs to neighborhood associations, community groups, and our local business community.”
- The money, in the minutes' words: “Action Requested: Adoption of a resolution to amend the contract with Green Built Alliance to 1) implement the Blue Horizons Project for an additional two years, 2) expand the scope of work and 3) authorize the City Manager to execute the amendment in an amount not to exceed a total contract amount of $100,000.”
What that means
- Consent agenda:
- Routine items Council approves together in one vote, without discussion. Any member can pull an item out for its own vote.
Official title: Resolution authorizing the City Manager to amend the contract with Green Built Alliance to implement the Blue Horizons Project for an additional two years, to expand the scope of the work and to authorize the City Manager to execute the contract amendment
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilman Young and carried unanimously.
Read the motion as recorded
“RESOLUTION NO. 19-107 - RESOLUTION AUTHORIZING THE CITY MANAGER TO AMEND THE CONTRACT WITH GREEN BUILT ALLIANCE TO IMPLEMENT THE BLUE HORIZONS PROJECT FOR AN ADDITIONAL TWO YEARS, TO EXPAND THE SCOPE OF THE WORK AND TO AUTHORIZE THE CITY MANAGER TO EXECUTE THE CONTRACT AMENDMENT”
Open the minutesConsent agenda, item G