June 11, 2019Asheville City Council
From the minutes, not yet reviewedCouncil approves a $202,064 contract with TAG Contracting Inc. for the Victoria Road Slope Stabilization Project.
Council voted to approve a contract with TAG Contracting Inc. for the Victoria Road Slope Stabilization Project, for $202,064.40.
- Passed with the routine items, in one vote, without discussion.
- What the City says it's for: “The contract will complete the stabilization work required to stabilize the slope adjacent to Victoria Road a main road used by AB Tech, Mission Hospital, Asheville High School and other residents and business owners in the area.”
- The money, in the minutes' words: “Motion to adopt a resolution authorizing the City Manager to execute a contract with TAG Contracting, Inc. in the amount of $168,387.00 and authorize the City Manager to approve an additional contingency amount of $33,677.40 (20%) for a total of $202,064.40, for the Victoria Road - Slope Stabilization Project.”
What that means
- Consent agenda:
- Routine items Council approves together in one vote, without discussion. Any member can pull an item out for its own vote.
Official title: Resolution authorizing the City Manager to execute a contract with TAG Contracting Inc. for the Victoria Road Slope Stabilization Project
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilman Kapoor and carried unanimously.
Read the motion as recorded
“RESOLUTION NO. 19-136 - RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH TAG CONTRACTING INC. FOR THE VICTORIA ROAD SLOPE STABILIZATION PROJECT”
Open the minutesConsent agenda, item C