October 24, 2023Asheville City Council
From the minutes, not yet reviewedCouncil approves a contract for the McCormick Field pre-construction services.
Council voted to approve a contract with Frank L. Blum Construction Company, in Association with W.C. Construction Company for the McCormick Field pre-construction services.
- Passed. Voted no: S. Antanette Mosley.
- What the City says it's for: “The lease was for a shorter duration in order to allow for planning to align with new MLB facility standards.”
Official title: Council authorized the City Manager to enter into a contract with Frank L. Blum Construction Company, in association with W.C. Construction Company for the McCormick Field pre-construction services, and further authorize the City Manager to execute any change orders that may arise during the project up to the contingency amount
Carried 6–1
From the minutes: This motion was seconded by Councilwoman Turner and carried on a 6-1 vote, with Councilwoman Mosley voting “no.”
Read the motion as recorded
“Councilwoman Roney moved to authorize the City Manager to enter into a contract with Frank L. Blum Construction Company, in association with W.C. Construction Company for the McCormick Field pre-construction services, and further authorize the City Manager to execute any change orders that may arise during the project up to the contingency amount.”
Open the minutesMotion text in the minutes