November 18, 2025Asheville City Council
From the minutes, not yet reviewedCouncil approves a contract with Bullington Construction Inc. for the Tropical Storm Helene Guardrail Repair contract.
- Passed with the routine items, in one vote, without discussion.
- What the City says it's for: “The award of this contract will allow for the replacement/repair of approximately 2,700 linear feet of guardrail and any needed posts and end sections to provide safety to the traveling public.”
- The money, in the minutes' words: “A 15% contingency of $27,440 is planned, which, with the bid total of $182,936, results in a maximum budget amount of $210,376.”
What that means
- Consent agenda:
- Routine items Council approves together in one vote, without discussion. Any member can pull an item out for its own vote.
More from the minutes
- “The storm damaged or destroyed approximately 2,700 linear feet of guardrail, along with numerous posts and end sections”
Official title: Resolution authorizing the City Manager to execute a contract with Bullington Construction Inc. for the Tropical Storm Helene Guardrail Repair contract, and further authorizing the City Manager to execute any change orders that may arise during the project up to the contingency amount
Carried unanimously, as part of the consent agenda
From the minutes: This motion was seconded by Councilwoman Roney and carried unanimously.
Read the motion as recorded
“RESOLUTION NO. 25-269 - RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH BULLINGTON CONSTRUCTION INC. FOR THE TROPICAL STORM HELENE GUARDRAIL REPAIR CONTRACT, AND FURTHER AUTHORIZING THE CITY MANAGER TO EXECUTE ANY CHANGE ORDERS THAT MAY ARISE DURING THE PROJECT UP TO THE CONTINGENCY AMOUNT”
Open the minutesConsent agenda, item J